Abatement Technologies

Project size: 91,751 ft²
Project cost: $1.8M
Completion date: Oct 2023
Abatement Technologies is a world leader in the design and manufacture of abatement products for removing harmful particles from any environment. They focus on products for health care, disaster restoration, abatement, remediation, and air purification.
In recent years, Abatement Technologies experienced a significant surge in demand, maxing out the capacity of its existing facility. This increase in sales and escalation in production requirements meant a much-needed physical expansion. In 2022, construction began on a 91,000-square-foot facility to house the company’s head office and production operation. Kraun Electric was the electrical contractor on the project.
Installation included:
- New state-of-the-art manufacturing facility and two-storey office
- High-voltage incoming power and customer-owned substation/high-voltage switch
- New machine commissioning and relocation of existing machines
- Automated lighting controls throughout the facility
- Installation of fire alarm system, generator, parking lot lighting, and EV chargers
Project Partners
- General Contractor: Scott Construction
- Consulting Engineer: NRG Consultants
- High-Voltage Subcontractor: SLH High Voltage and Civil
- Telecom Cabling Subcontractor: Systemmacs Inc.
- Security & Access Control Subcontractor: Alliance Security Niagara